35 Multi-Modal Logistics Parks (MMLP) Projects to be developed under Public Private Partnership (PPP) across the country

New Delhi: Cabinet Committee on Economic Affairs (CCEA) on October, 2017 had approved Phase-I of Bharatmala covering 24,800 km of roads under Bharatmala Pariyojana in addition to 10,000 km of residual NHDP, at an financial outlay of Rs. 5,35,000 Crores. Apart from above highways projects, CCEA also mandated MoRT&H to develop 35 Multi Model Logistics Parks (MMLP) across the country. The list of 35 MMLPs is provided at Annexure – I.  The status of 35 MMLPs along with land acquisition and the status of detailed technical assessment is provided at Annexure – II.  The status of detailed technical assessment is provided at  Annexure – II.

35 MMLPs being implemented by MoRTH are to be developed under Public Private Partnership (PPP) on Design, Build, Finance, Operate and Transfer (DBFOT) mode.  The bidding documents (The Model Concession Agreement and Request for Proposal) for these 35 MMLPs is under finalization.  Based on outcome of DPR/Feasibility Studies and approved bidding document, the tender will be invited from companies.

 

 

Annexure – I

ANNEXURE REGARDING MULTI – MODAL LOGISTICS PARKS  

 

Sr No   Location
1 Nagpur  
2 Chennai  
3 Bangalore  
4 Indore  
5 Mumbai  
6 Hyderabad  
7 Coimbatore  
8 Pune  
9 Surat  
10 Sangrur  
11 Delhi-NCR  
12 North Gujarat  
13 Jaipur  
14 Kolkata  
15 Ambala  
16 Jagatsinghpur  
17 Nashik  
18 Kota  
19 Panaji  
20 Hisar  
21 Visakhapatnam  
22 Bhopal  
23 Sundargarh  
24 Bhatinda  
25 Solan  
26 Rajkot  
27 Raipur  
28 Jammu  
29 Kandla  
30 Cochin  
31 North Punjab  
32 Vijayawada  
33 Patna  
34 Valsad  
35 Guwahati  

Annexure – II

ANNEXURE REGARDING MULTI – MODAL LOGISTICS PARKS  

 

Sr No          Location Status of Land for MMLP
1 Nagpur 346 acres of land identified for development of MMLP and is in possession of  Jawaharlal Nehru Port Trust (JNPT).
2 Chennai Total area identified for development of MMLP is 158 Acres. Out of this, 122 acres is with Chennai Port Trust (ChPT). Remaining 36 acres is under acquisition byTamil Nadu Industrial Development Corporation (TIDCO), Govt. of Tamil Nadu.
3 Bangalore Land of 400 acres identified for development of MMLP at Mudalinganahalli. Land acquisition process is to be initiated by Karnataka Industrial Area Development Board (KIADB), Govt. of Karnataka.
4 Indore DPR/ Feasibility study in progress. Land parcel to be identified
5 Mumbai DPR/ Feasibility study in progress. Land parcel to be identified
6 Hyderabad DPR/ Feasibility study in progress. Land parcel to be identified
7 Coimbatore DPR/ Feasibility study in progress. Land parcel to be identified
8 Pune DPR/ Feasibility study in progress. Land parcel to be identified
9 Surat DPR/ Feasibility study in progress. Land parcel to be identified
10 Sangrur DPR/ Feasibility study in progress. Land parcel to be identified
11 Delhi-NCR Pre-feasibility study is in progress. Land parcel to be identified
12 North Gujarat Pre-feasibility study is in progress. Land parcel to be identified
13 Jaipur Pre-feasibility study is in progress. Land parcel to be identified
14 Kolkata Pre-feasibility study is in progress. Land parcel to be identified
15 Ambala Pre-feasibility study is in progress. Land parcel to be identified
16 Jagatsinghpur Pre-feasibility study is in progress. Land parcel to be identified
17 Nashik Pre-feasibility study is in progress. Land parcel to be identified
18 Kota Pre-feasibility study is in progress. Land parcel to be identified
19 Panaji Pre-feasibility study is in progress. Land parcel to be identified
20 Hisar Pre-feasibility study is in progress. Land parcel to be identified
21 Visakhapatnam Pre-feasibility study is in progress. Land parcel to be identified
22 Bhopal Pre-feasibility study is in progress. Land parcel to be identified
23 Sundargarh Pre-feasibility study is in progress. Land parcel to be identified
24 Bhatinda Pre-feasibility study is in progress. Land parcel to be identified
25 Solan Pre-feasibility study is in progress. Land parcel to be identified
26 Rajkot Pre-feasibility study is in progress. Land parcel to be identified
27 Raipur Pre-feasibility study is in progress. Land parcel to be identified
28 Jammu Pre-feasibility study is in progress. Land parcel to be identified
29 Kandla Pre-feasibility study is in progress. Land parcel to be identified
30 Cochin Pre-feasibility study is in progress. Land parcel to be identified
31 North Punjab Pre-feasibility study is in progress. Land parcel to be identified
32 Vijayawada Based on prefeasibility studies, MMLP currently not feasible.
33 Patna Based on prefeasibility studies, MMLP currently not feasible.
34 Valsad Based on prefeasibility studies, MMLP currently not feasible.
35 Guwahati MMLP under construction by National Highways and Infrastructure Development Corporation (NHIDCL). 190 acres of land identified for development of MMLP and is in possession of  Govt. of Assam

 

 

36 Nagpur 346 acres of land identified for development of MMLP and is in possession of  Jawaharlal Nehru Port Trust (JNPT).
37 Chennai Total area identified for development of MMLP is 158 Acres. Out of this, 122 acres is with Chennai Port Trust (ChPT). Remaining 36 acres is under acquisition byTamil Nadu Industrial Development Corporation (TIDCO), Govt. of Tamil Nadu.
38 Bangalore Land of 400 acres identified for development of MMLP at Mudalinganahalli. Land acquisition process is to be initiated by Karnataka Industrial Area Development Board (KIADB), Govt. of Karnataka.
39 Indore DPR/ Feasibility study in progress. Land parcel to be identified
40 Mumbai DPR/ Feasibility study in progress. Land parcel to be identified
41 Hyderabad DPR/ Feasibility study in progress. Land parcel to be identified
42 Coimbatore DPR/ Feasibility study in progress. Land parcel to be identified
43 Pune DPR/ Feasibility study in progress. Land parcel to be identified
44 Surat DPR/ Feasibility study in progress. Land parcel to be identified
45 Sangrur DPR/ Feasibility study in progress. Land parcel to be identified
46 Delhi-NCR Pre-feasibility study is in progress. Land parcel to be identified
47 North Gujarat Pre-feasibility study is in progress. Land parcel to be identified
48 Jaipur Pre-feasibility study is in progress. Land parcel to be identified
49 Kolkata Pre-feasibility study is in progress. Land parcel to be identified
50 Ambala Pre-feasibility study is in progress. Land parcel to be identified
51 Jagatsinghpur Pre-feasibility study is in progress. Land parcel to be identified
52 Nashik Pre-feasibility study is in progress. Land parcel to be identified
53 Kota Pre-feasibility study is in progress. Land parcel to be identified
54 Panaji Pre-feasibility study is in progress. Land parcel to be identified
55 Hisar Pre-feasibility study is in progress. Land parcel to be identified
56 Visakhapatnam Pre-feasibility study is in progress. Land parcel to be identified
57 Bhopal Pre-feasibility study is in progress. Land parcel to be identified
58 Sundargarh Pre-feasibility study is in progress. Land parcel to be identified
59 Bhatinda Pre-feasibility study is in progress. Land parcel to be identified
60 Solan Pre-feasibility study is in progress. Land parcel to be identified
61 Rajkot Pre-feasibility study is in progress. Land parcel to be identified
62 Raipur Pre-feasibility study is in progress. Land parcel to be identified
63 Jammu Pre-feasibility study is in progress. Land parcel to be identified
64 Kandla Pre-feasibility study is in progress. Land parcel to be identified
65 Cochin Pre-feasibility study is in progress. Land parcel to be identified
66 North Punjab Pre-feasibility study is in progress. Land parcel to be identified
67 Vijayawada Based on prefeasibility studies, MMLP currently not feasible.
68 Patna Based on prefeasibility studies, MMLP currently not feasible.
69 Valsad Based on prefeasibility studies, MMLP currently not feasible.
70 Guwahati MMLP under construction by National Highways and Infrastructure Development Corporation (NHIDCL). 190 acres of land identified for development of MMLP and is in possession of  Govt. of Assam

*****

 

This information was given by Union Minister for Road Transport and Highways, Shri Nitin Gadkari in a written reply in the Lok Sabha.